BSR timelines

Building Safety Regulator Timelines

Why Collaboration is the Key to Safer Buildings

Since the introduction of the Building Safety Act 2022, the construction industry has been under immense pressure to ensure that high-rise residential buildings meet the new safety standards. The Building Safety Regulator (BSR) has set strict timelines to bring about these necessary changes, but progress has been slow. Why? Because too often, stakeholders—developers, contractors, architects, engineers, and regulatory bodies—aren’t working together effectively. The reality is simple: if we don’t collaborate, people’s safety is at risk.

Understanding BSR Timelines

The BSR’s regulatory framework is designed to ensure building safety through a structured, multi-stage process:

  • Registration Deadline: Since April 2023, all higher-risk residential buildings must be registered with the BSR. The deadline was October 2023, and failure to comply could lead to investigations and prosecution.
  • Gateway Process: The Act introduces three key gateways:
  • Gateway One (Planning stage): Ensures that fire safety is embedded in early designs.
  • Gateway Two (Pre-construction): Requires detailed design and safety information before building work begins.
  • Gateway Three (Pre-occupation): Confirms that a building is safe before it can be occupied.

Each gateway has a 12-week approval window, which means delays anywhere in the process can create a backlog that pushes projects further out. With thousands of buildings needing remediation or retrofit, slow progress isn’t just inconvenient—it’s dangerous.

Why the Process is Taking Longer Than Expected

Despite clear timelines, the remediation and retrofit processes are still difficult to achieve. Maybe the biggest reason for this is a lack of collaboration.

  • Fragmented Responsibilities: Too often, key players work in silos, failing to coordinate with others. This results in delays in planning, approval, and execution.
  • Compliance Confusion: Many firms are still unsure of what exactly is required at each stage, leading to back-and-forths with regulators and more delays.
  • Design vs. Reality Issues: On-site conditions don’t always match original plans, requiring last-minute changes. Without good communication between design and construction teams, these discrepancies stall progress.
  • Supply Chain Bottlenecks: Materials and compliant solutions need to be sourced efficiently. When stakeholders don’t communicate early, procurement delays add to the timeline.

In short, failing to work together means failing to meet deadlines—putting residents at risk for longer than necessary.

Case Study: Gemini Park – A Lesson in Collaboration

The Gemini Park project is a prime example of how working together can overcome significant remediation challenges. The task? Replacing non-compliant decking on existing structures while contending with multiple complexities:

  • Original Design Constraints: The steel frames were designed for timber joists, limiting options for new, compliant materials.
  • Structural Variations: Balcony build-ups didn’t match original plans, requiring adaptable solutions.
  • Large Spans & Cantilevers: New decking needed to meet significant structural demands.

By fostering collaboration between engineers, architects, and contractors, a tailored solution was developed using the BalcaSmart® Aluminium Decking System. This involved:

Because the team worked together from the outset, they were able to anticipate challenges, implement an effective solution, and deliver a safe, compliant, and aesthetically pleasing outcome for residents.

Insights from Industry Leaders

Recent discussions among industry professionals have highlighted the critical importance of collaboration in accelerating building safety remediation. Anthony Walker emphasises the need for a unified approach, stating, “Building safety remediation requires all stakeholders to work together seamlessly to meet the stringent deadlines set by the BSR.” 

Similarly, Simon Marsh underscores the role of effective communication, noting, “Clear and consistent communication between developers, contractors, and regulatory bodies is essential to navigate the complexities of the new safety standards.” 

The Power of Collaboration

While challenges remain, the industry has a real opportunity to speed up remediation by embracing collaboration at every level. By fostering stronger partnerships, aligning on compliance from the outset, and improving communication across all stakeholders, we can drive meaningful progress.

  1. Communicate Early and Often: Regular, transparent discussions between all parties involved in a project can prevent bottlenecks and unexpected delays.
  2. Plan for Compliance from Day One: Ensuring that all designs align with regulatory expectations early will save time and money down the line.
  3. Prioritise Flexibility in Solutions: Many existing structures present unforeseen challenges. Teams need to work together to develop adaptable, compliant solutions rather than scrambling for fixes last-minute.
  4. Break Down Industry Silos: Engineers, architects, contractors, and developers must stop working in isolation. A shared commitment to safety and efficiency will drive real progress.

By engaging all stakeholders throughout the entire process, we can offer comfort to residents experiencing a stressful time, ensuring they feel informed and supported.

BSR timelines exist for a reason: people’s safety. But deadlines alone won’t get us there—collaboration will. The Gemini Park project proved that when industry professionals come together, even the most complex remediation challenges can be overcome.